Scope of works
The Curley Group was appointed by ICON, working on behalf of BT Group, to bring the external areas of BT’s Glasgow centre up to date. Our package ran from August to October 2026 and covered:
- Demolition and removal of the existing fence line
- Installation of 150 linear metres of palisade fencing to form new secure compounds
- New site entrance gates
- Installation of 144 linear metres of crash barrier in the car park
- New white lining throughout the car park
- Remediation works to existing paths, walkways and boundary walls
Fencing, compounds & gates
We took down the old fence line and replaced it with 150 linear metres of galvanised palisade fencing, laid out to form new compounds within the site. New entrance gates were installed to complete the secure perimeter.
Car park safety
In the car park we installed 144 linear metres of crash barrier to protect buildings, pedestrians and equipment, and carried out new white lining to give clear, safe parking and traffic routes.
Paths, walkways & boundary walls
Sections of the site’s brick boundary walls had deteriorated, with loose and missing bricks and copings and heavy vegetation growth. We carried out remediation works to the walls, rebuilding damaged sections and finishing them with new copings, alongside repairs to the existing paths and walkways so the whole site is safe and up to date.
Working on a live BT site
The works were delivered to a tight programme on a fully operational BT site. We planned each stage around BT’s staff and day-to-day operations, keeping access open and work areas safe so the site could keep running as normal throughout.