Scope of works
The Curley Group was appointed by ICON, working on behalf of BT Group, to bring BT’s Bradwell Abbey centre in Milton Keynes up to date. Our package ran from August to October 2026 and covered:
- Design and construction of a brand new car park for HGVs
- All drainage requirements for the new car park
- Installation of 250 linear metres of palisade fencing to form new compounds
- New site entrance gates
- Remediation works to existing paths and walkways
A new HGV car park
We designed and built a brand new car park, including all the drainage needed for HGV vehicles. The area was cleared, a stone sub-base laid, channel drainage installed and the surface finished in tarmac.
Fencing, compounds & gates
We installed 250 linear metres of palisade fencing to form new compounds, along with new site entrance gates.
Paths & walkways
We carried out remediation works to the site’s existing paths and walkways, bringing the whole site up to date.
Working on a live BT site
The works were delivered to a tight programme on a live BT site, with our team working around the site while it stayed in use.